DEPARTMENT | PROJECT COST |
---|---|
School Education & Literacy Department | PKR 1,082 Million |
Improve the functioning of TTIC Hussainabad by introducing innovations, modernizing the education system, addressing management gaps, maintaining and upgrading the Institutes' building and facilities, and cooperatively working along with teachers, Institutes' staff, Institutes' management committees, surrounding communities and all relevant tiers of the Authority. Furthermore, below given are summarized project benefits/outcomes:
Installation Period (10 months)
Installation works includes but not limited to rehabilitation & revamping of physical infrastructure of the institute and providing furniture, equipment, MIS, hiring of administrators & staff, setting-up labs, computer labs and subscription of international journals for research work.
O&M Period (10 years from completion of Installation works)
Unsolicited proposal has been received by the Education department which is under evaluation and is being considered under PPP mode. The same was placed before the Policy Board during its 20th Meeting on March 8, 2017 and has been approved for investor solicitation. Further the Policy Board has advised to initiate private partner solicitation for a teachers training institute per district including Professional Development Center. Transaction advisory being conducted. The project is expected to be launched by May / June 2018.
The School Education & Literacy Department executed Management Contract on 1st March 2019.
Subsequently, Supplemental and Second Supplemental to Management Contract was executed on 13th June 2019 and August 2021, respectively.
The PPP Policy Board in its 27th meeting held on 13th December 2018 approved the Project.
The Project was launched for investor solicitation in May 2018 in pursuance to SPP rules 2010. Since the project was initiated based on unsolicited proposal from "Durbeen", the pre-qualification process was initiated.
Subsequently, RFP was issued to sole bidder i.e. Durbeen on 30th May 2018. The procurement process was concluded in November 2018.
Independent Expert Firm: AASA Consulting
Independent Auditor: A.F. Ferguson Chartered Accountants
The substantial completion of installation works completed by Durbeen on 15th July 2020 and the TTIC Hussainabad is under operational phase with achievement of KPIs successfully todate.
09-Nov-2021